* Status on May 2019:. DPR prepared with estimated cost of Rs. 5341.68 Cr. and submitted to Board on 04.08.2017 for sanction. Railway Board query about cost has been replied on 10.10.2017. MRIDL has been asked to study & decide whether they would like take up this project. They have submitted preliminary report. Central Railways comments on the same have been sent to Board.