Saurashtra Cement To Shut Down Gujarat Plant For Annual Maintenance
2017-12-20 Shutdown/Strikes/Disturbances Building Materials Western India
Saurashtra Cement Limited has informed to take up annual maintenance shutdown of the Kiln and all the downstream equipment situated at the factory premises in Ranavav (Gujarat) tentatively from 8th January 2018. This maintenance shutdown is planned for about 20 days and will depend on the conditions of the machinery found during the inspection.
However, cement grinding and cement packing sections will continue to operate meeting all the cement dispatch, requirements. Hence there will be no impact on the sales volume.