Factory - I
Plinth beam and Basement slab concrete work finished, Column work in double height area and PEB fabrication work are in progress.
Factory - II
Civil work, PEB & Roofing work finished, Pump room Fire pump installed and tested, Fixing of door and window work completed, HVAC work finished along with testing, Plumbing and Sanitary fitting installation work finished, Internal Fire hydrants work finished with the installation of Fire hydrant assembly, FAS work finished along with Smoke detectors and other required accessories, Fire Sprinkler work finished and Machine installation work is in progress.
Infra, Utility work
Road PCC work is in progress, Part of Rainwater harvesting pit work finished alongwith filter media and the balance work is in progress, External Plumbing work and drain work are in progress, Front side Compound wall completed am! other side Compound wall is in progress.
Warehouse
Warehouse activities in Chakan Plant will commence in the first week of June 2019. Accordingly, materials will also be shifted to New Chakan Plant from other locations.
Company also under process to expedite the manufacturing operations at Chakan Plant.