DBL Receives Provisional Completion Certificate For A Project In UP
2019-02-14 Projects Construction Northern India
Dilip Buildcon Limited (DBL) informs that, the project "Four lanning of Ghaghra Bridge to Varanasi section of NH - 233 from Km 121.800 to Km 180.420 (Package - I) from Ghaghra Bridge abutment on Basti side to Bhudanpur Urban section in the state of Uttar Pradesh under NHDP Phase - IV on EPC Mode" has been provisionally completed. The Provisional Completion Certificate has been issued by the authority and has declared the project fit for entry into commercial operation. The details of the project are as under:
Project | Mode | Project cost (in cr) | Appointed date | Scheduled completion date | Provisional completion date |
Four Inning of Ghaghra Bridge to Varanasi section of NH - 233 from Km 121.800 to Km180.420 (Package - I) from Ghaghra Bridge abutment on Basti side to Bhudanpur Urban section in the state of Uttar Pradesh underNHDP Phase - IV on EPC Mode | EPC mode | 674.34 | 15.12.2015 | 22.03.2019 | 04.02.2019 |